Name of Project:

King County West Point Fiber Construction Management

Location:

Seattle, WA

Owner:

King County

Other Companies Involved:

Vanir Construction

Date:

2011

Scope:

Construction Management services, through Vanir Construction Management, for King County Ovation Network SCADA Layer Replacement.  This included performing the following tasks:

1.   Review contract specifications and contract drawings

2.   Coordinate between CH2M Hill Engineers and Contractors

3.   Write and submit inspector's daily construction report to King County

4.   Submit detailed photographs of work performed daily

5.   Verify completed work and fiber communication test reports

Electrical Inspection Services for upgrades to the County's Sumitomo FutureFLEX ABF network.  This includes QA/QC review and comments for construction documents generated by the contractor implementing control panel modifications in the West Point Treatment Plant Main Control room.

 

Daily inspection duties include:  Monitor and report ongoing field-testing, coordination work.  Prepare Daily Report in the project record.  Maintain the following records in the document files:  Test results, acceptance certificates and reports from public agency inspectors, discrepancy reports, approved shop drawings, safety reports, photo logs assist in resolution of construction problems.  Report field conditions that prevent construction to original design.  Log all equipment on the job site, and record construction personnel on site.  Record all activities worked on in scheduled section of the project Daily report.  Record all material deliveries, visitors, construction activities for compliance with contract documents.  Observe safety regulations and notify Contractor of problem areas.  Take digital photos and enter in Photo Log.

 

Final inspection duties include:  Perform closeout and final inspections, maintain log book, develop punch list.

 

 

SeaTacBluefield Site 2Westpoint